Finished Project Gallery | Remington Ranch Detention

This project consist of excavation and hauling offsite 18,000 cubic yards of material to include installation of back slopes, concrete pilot channel, and outfall pipe to include trash collection system. This was a 60 day calendar project. The attached picture show the finished project after hydro mulch.